Free planning tool Updated August 2026

Whole House Generator Cost Calculator

Get an itemized installation range in under two minutes. Size the system, account for site work, and see where the budget actually goes.

Start my estimate 8 project controls · No signup · No sales call

01 Live planning estimate

Build your project scope.

Adjust eight project controls. Every change updates the recommended size, range, and itemized costs—no email required.

2,200 sq ft
8007,000 sq ft
Backup coverage
Fuel source
30 ft

A longer run usually adds pipe, trenching, and labor.

Adjacent250 ft
6+Visible cost lines
50State adjustments
3Budget scenarios

Built for planning before contractor bids

02 Installed-cost benchmarks

Whole-house generator cost by size.

These planning bands use the same model as the calculator: automatic transfer, natural gas, a 30 ft fuel run, standard site work, and the Texas location factor.

Illustrative generator equipment and installed project ranges by rated capacity
Rated sizeCommon planning useEquipment allowanceTypical installedInstalled range
10kWCritical circuits$2,900$4,800$11,850$7,480$15,890
14kWEssentials + selected loads$3,520$5,800$12,880$8,210$17,120
18kWManaged home coverage$4,140$6,800$13,910$8,950$18,350
22kWCommon whole-home planning band$4,760$7,800$14,940$9,680$19,570
26kWLarger loads or added headroom$5,380$8,800$15,970$10,420$20,800
38kWLarge-home / liquid-cooled band$7,240$11,800$19,060$12,620$24,490

Capacity is not determined by square footage alone. Use these rows to frame a budget, then confirm size with an on-site electrical load calculation.

03 Read the number

The generator is only part of the bill.

A useful estimate separates the equipment from the work required to make it operate safely at your home.

01 / System size

Capacity changes more than the machine.

More simultaneous loads can require a larger generator, transfer equipment, conductors, and heavier electrical work. Square footage starts the conversation; the actual load plan finishes it.

Often 35–50% of total
02 / Fuel & wire distance

Every extra foot can carry two scopes.

The route from meters and panels can add fuel pipe, conductor, trenching, restoration, regulators, and utility coordination. Distance is inexpensive to measure early and costly to discover late.

Distance compounds labor
03 / Site complexity

The widest unknown is usually outside.

Slopes, limited access, drainage, setbacks, anchoring, older panels, and local review can widen the final quote. A clear site scope makes contractor bids easier to compare.

Plan the site before the bid

04 Compare bids fairly

Take the same scope to every contractor.

0 / 10 checked

Print this list with your current estimate and mark the same inclusions on every bid.

05 How it works

A range you can audit.

The model sizes a planning system from home area and coverage, then adds each project component. Labor-sensitive lines receive a broad state factor; equipment remains visible and unchanged.

  1. 1
    Size the planning load

    Square footage and coverage produce an indicative kW band—not an electrical design.

  2. 2
    Build the project scope

    Equipment, switch, electrical, fuel, pad, permits, and optional panel work are priced separately.

  3. 3
    Apply local uncertainty

    A state factor adjusts labor-sensitive lines before low, typical, and high totals are summed.

Example cost anatomy16 kW · TX
Generator equipment
38%
Electrical & switch
34%
Fuel connection
13%
Site & permits
15%
Model2026.08Transparent assumptions

Public model notes

What the calculator assumes

Market
United States planning estimate
Model version
2026.08 · reviewed August 2026
Equipment
Capacity-based allowance; manufacturer and dealer pricing varies
Location factor
Broad labor-sensitive planning factor, not a local bid or published cost index
Excluded decisions
Final load, fuel pressure, conductor size, setbacks, and code compliance

06 Before you request bids

Questions worth answering first.

01How much does a whole-house generator cost installed?

A common planning range is roughly $8,000 to $16,000, but larger units, long fuel runs, difficult sites, and panel work can push the total higher. The calculator itemizes those variables instead of applying one national average to every house.

02What size generator does a 2,000-square-foot house need?

Square footage is only a starting point. Many projects fall around 14–22 kW depending on HVAC, wells, electric appliances, and which circuits must run together. A licensed installer should complete an electrical load calculation before equipment is selected.

03Is the transfer switch included in the estimate?

Yes. The calculator includes either a manual or automatic transfer-switch allowance as its own visible line item. The final switch type and amperage must match the electrical design and local requirements.

04Why does fuel-line distance change the price?

Longer runs can require more pipe, larger pipe sizing, trenching, regulators, utility coordination, and labor. The calculator uses distance as a planning signal; it does not determine pipe size or fuel pressure.

05Does a standby generator require a permit?

Most installations involve electrical permits and inspections, and many also need fuel, mechanical, zoning, or HOA approval. Requirements and fees are local, so the estimate includes a range rather than a single fee.

i

Know what this number is—and is not. This is a budgeting model, not a bid, load calculation, fuel-system design, or code review. Ask a licensed local installer to verify equipment sizing and every site requirement.

Review manufacturer installation factors ↗